Footings can be poured when the temperature
is 20 degrees Fahrenheit or above, however the following precautions must
be adhered to:
Concrete shall be maintained at a
temperature of not less than 50 degrees Fahrenheit for a minimum of 3
consecutive days after placement of concrete.
INSULATED BLANKETS MUST PROTECT THE
CONCRETE AND FORMS LEFT IN PLACE.
The hole should not be left open for more
than 24 hours. Protection must be provided to keep soil from freezing with
STRAW or INSULATED BLANKETS.
Foundation walls can be poured when the
temperature is 40 degrees Fahrenheit or above.
Concrete shall be maintained at a
temperature of not less than 50 degrees Fahrenheit for a minimum of 7
consecutive days.
INSULATED BLANKETS SHALL BE SECURELY
FASTENED TO BOTH SIDES AND THE FORMS MUST BE LEFT IN PLACE.
After the first frost, it is the discretion
of the Building Official if flat work can continue. Flat work is allowed
if the temperature of the concrete is maintained at 50 degrees for 7
consecutive days after concrete placement.
The use of salamanders, or other equipment
that exhaust flue gases into the area above concrete floors must be
avoided, because of the danger of carbonation to the fresh concrete.
The I.C.C. Code Council and American
Concrete Institute ACI – 318 provides for alternates for the above. High
early strength may be used to substitute the following guidelines. An
increase in the amount of cement to a minimum of a 6-bag mix and
maintaining the concrete at 50 degrees for 3 consecutive days provides an
option for the builders. Additionally, admixtures for high early strength
may be added in accordance with the manufactures requirements.
The use of visqueen and straw are not an
acceptable means of protection, INSULATED BLANKETS ONLY.
Please contact the Building Department
prior to ordering concrete.
-
Drain
tile shall be installed around the outside of the foundation adjacent to
the footings, leading to a sump pump, which should discharge into an
approved drainage facility. Drainage must be provided on all basement
and crawl spaces when encompassing a habitable space. With the prior
approval of the Building Official, drain tile may be "daylighted",
at his sole discretion.
-
All
poured crawl spaces must be provided with a drain tied into the tile
which is to be located at the interior of the footing. The drain tile is
to then discharge into a sump pit.
-
In
no case shall footing drains be connected to any sanitary sewer system,
or septic system.
-
Footings
for single family dwelling units containing no basement or crawl space
are permitted provided that it has a trench footing that is a minimum
12" width and a minimum of 42" depth. This depth is to be
measured below grade.
-
Bottom
of footings, shall be not less than three feet six inches (3'6")
below finished grade, except where placed on solid bed rock. Minimum
size of footings shall be "10 x 20" with standard
"keyway", or as approved by the building official.
-
A
foundation wall is required under all stoops supporting a roof.
-
Foundation
shall be backfilled with clean fill. Do not use debris for backfilling.
-
All
columns supporting beams must rest on a minimum 36" x 36" x
12" deep concrete pier footing. Rivet, weld or bolt top of steel
column to steel girders (or lag screw to wood girders) and anchor bottom
by bolts or embed in concrete.
-
All
floor slabs shall be a minimum of 4" thick including all accessory
structures. All slabs shall have a minimum of four-inch stone base.
-
When
concrete floor is installed in heated areas, a vapor barrier must be
provided.
-
The
wing walls used to support stoops must be properly reinforced.
-
Detached
garages shall have a minimum 12" by 12" trench footing with a
minimum 4" slab and 6" stone base.
-
An
attached garage shall be completely separated from the residence and its
attic by a minimum 5/8" drywall applied to the garage side with
joints properly taped and cemented, or equivalent. Sills of all door
openings between the garage and adjacent interior habitable space of
Group R shall be raised not less than four inches above the garage
floor.
-
Concrete
shall be placed only on clean compacted fill (compacted to 95% Proctor
density) stone fill or virgin clay free from any vegetation debris or
organic soils.
-
All
structural pier drawings shall be designed and stamped by a registered
design professional.
-
All
wood decks enclosed or otherwise after removal of organic vegetation
shall have installed a minimum of two inch stone base over six mil
visqueen or as approved by the AHJ. (exception to the above where the
entire space under the deck is readily accessible).